| Service name: |
New Power Connection Application
|
| Service description: |
Connection of electricity for new premise |
| Process description: |
- Submission of required documents for connection of electricity service.
- Obtaining an appointment for inspection.
- Completion of site inspection & approval from concerned parties.
- Approval of electricity schemes/drawings.
- Notifying client of required fees.
- Connect Electricity.
|
| Fees: |
| Fee | Amount Dhs | payable for |
| Cost verified based on load, cable size & length after completion of all required procedures |
unspecified |
TAQA Distribution |
|
| Service access: |
Service Inquiry: TAQA Distribution Contact Center (800 2332) 24 Hours / 7 days Applying for Service: Technical counter , Al Saad Branch, Al Hayar Branch and Al Wagan Branch |
| Working hours: |
Technical counter; external branches during official working hours (7AM – 3 PM) from Sunday to Thursday. |
| Service availability : |
Individuals; Corporate |
| Service Duration : |
45 Days |
Required documents:
| Documents/Type | Residential | Governmental | Mosques | Farms/Wells | Temporary | Tents |
| Letter From Al-Ain Municipality |
|
|
|
|
|
|
| Site Plan |
|
|
|
|
|
|
| Copy Of Owner's ID |
|
|
|
|
|
|
| Letter From Company |
|
|
|
|
|
|
| Copy Of Trade License |
|
|
|
|
|
|
| Letter From Islamic Affairs Authority |
|
|
|
|
|
|
| Copy Of Construction Permission |
|
|
|
|
|
|
| Copy Of Authorized Signatures |
|
|
|
|
|
|
Electrical Installation Certificate
Electrical Installation Test Report
Inspection Report
Inspection Required Documents
Installation Testing Report